Bach Dang Bridge was built to complete the route connecting Ha Long City with the Hanoi – Hai Phong expressway system and to connect the economic triangle of Hanoi – Hai Phong – Quang Ninh.
Investors: Trungnam Group – SE Corp. – CIENCO 1 – Cuong Thinh Thi – Cai Mep – Phuc Loc – Cong Thanh – Phuong Thanh
Scale:
- - Permanent construction using reinforced concrete and prestressed reinforced concrete
- - Main bridge length: 3.054 km; width: 25 m; designed for 4 lanes; maximum speed: 100 km/h
- - Navigation clearance: 250 m wide, 48.4 m high; designed to withstand Level VIII earthquakes
- - The bridge has 3 pylons; approach roads on both sides total 2.357 km
Investment form: BOT
Location: Hai Phong City and Quang Ninh Province
Commencement: 25/02/2015
Inauguration: 01/09/2018