index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1

EVN'S 172 MW CURTAILMENT OF TRUNG NAM NINH THUAN IS UNJUSTIFIED

Presenting the National Assembly's Ombudsman Report at the 21st session of the National Assembly Standing Committee on the afternoon of March 15, Head of the Ombudsman Board Duong Thanh Binh stated that implementing Conclusions from the 18th and 20th Sessions, on March 8, 2023, the Ombudsman Board chaired a working session with relevant ministries and sectors regarding the petition of Trung Nam Thuan Nam Solar Power Company Limited in Ninh Thuan.

Causing Major Economic Damage to the Enterprise

The report stated that the 450 MW Solar Power Plant Project combined with investment in the 500 kV Thuan Nam Substation and 500 kV, 220 kV transmission lines connecting to the national grid was approved by the Prime Minister for planning supplementation and synchronized commissioning in 2020 to transmit and release full capacity of this solar plant and other regional renewable energy projects.

The project was guided by the Ministry of Industry and Trade, and the Ninh Thuan Provincial People's Committee organized bidding to select the investor in accordance with legal regulations. To date, the project has operated effectively, making major contributions to the national power grid.



The project has been in commercial operation for over 2 years, but EVN has not yet accepted management of the substation and transmission line system invested and constructed by Trung Nam Thuan Nam Company per project commitments, causing the investor severe difficulties and immense pressure regarding bank loan repayments.


Based on reports and exchanges with agencies during the working session, the Ombudsman Board recognized that EVN's suspension of dispatching 172 MW violates Article 4 of Prime Minister's Decision 13/QD-TTg dated April 6, 2020 on incentive mechanisms for solar power development in Vietnam, contradicts the signed Power Purchase Agreement between parties, causes major economic damage to Trung Nam Thuan Nam Company, wastes social investment resources, and adversely impacts the investment environment and provincial budget revenue in Ninh Thuan.

Furthermore, EVN's claim that suspending 172 MW dispatch is due to the lack of an electricity pricing mechanism lacks legal basis, because the Ministry of Industry and Trade issued Circular No. 15 dated October 3, 2022 regulating method for calculating electricity generation price frames for transitional solar and wind power plants, and Decision No. 21 dated January 7, 2023 on the price frame for transitional solar and wind power plants. This provides an important legal basis for EVN to finalize tariff agreements for transitional solar and wind power plants.   

Regarding EVN's failure to accept, manage, and operate the 500 kV Substation and connecting 500 kV and 220 kV transmission lines, the Ombudsman Board noted that, in actual operation, grid dispatching at the station is currently handled by EVN's transmission unit hired by Trung Nam Thuan Nam Company to ensure national grid safety for this special key work. However, because the law lacks specific regulations on asset transfer in this scenario, EVN has not yet accepted management and operation.

Need for Early Issuance of Regulations and Guidelines

From the above reality, the Ombudsman Board requests the Government and the Prime Minister to continue providing direction to urgently issue regulations and guidelines as a legal basis for transferring the 500 kV Thuan Nam Substation and 500 kV, 220 kV infrastructure invested in and constructed by Trung Nam Thuan Nam Company to EVN for takeover, management, and operation.

Urge and direct the Ministry of Industry and Trade to instruct EVN to definitively resolve the grounded petitions of Trung Nam Thuan Nam Solar Power Co., Ltd. regarding early dispatch of the 172 MW capacity of the Solar Power Plant in Phuoc Minh Commune, Thuan Nam District, Ninh Thuan Province, ensuring legal compliance and honoring contractual PPA commitments; guide and instruct EVN to urgently finalize electricity purchase price determinations for transitional solar and wind power plants.

Direct Ninh Thuan Provincial People's Committee to coordinate closely with the Ministry of Industry and Trade and the investor of Trung Nam Thuan Nam Solar Power Plant to finalize project documentation for acceptance of completed construction items per Government Decree 06 of 2021 on construction quality management and maintenance.

Additionally, the Ombudsman Board noted that to meet power market supply shortages and satisfy conditions for renewable energy incentive mechanisms in general and solar power in particular, many projects, right after policy approval, initiated investment and construction prior to authorities completing land allocation, land lease, or land-use conversion procedures.

" This is the cause of several complex social order and security incidents in some localities with wind and solar power projects, requiring competent local authorities to urgently complete land allocation, land lease, and land conversion documentation while strictly handling violations of construction and land regulations," Mr. Duong Thanh Binh stated.

TOP