HCMC 10,000-BILLION-VND FLOOD CONTROL PROJECT AWAITS CAPITAL DISBURSEMENT

HCMC Vice Chairman Bui Xuan Cuong listening to Trungnam Group presenting 10,000-billion-VND flood control project

Vice Chairman of HCMC People's Committee Bui Xuan Cuong (far left) listening to the project owner present the 10,000-billion-VND flood control project

On the morning of March 11, Vice Chairman of HCMC People's Committee Bui Xuan Cuong, together with relevant departments and agencies, conducted an on-site inspection of tidal sluice gates under the 10,000-billion-VND flood control project. The delegation began inspecting progress at Ben Nghe sluice gate (connecting District 1 and District 4) and concluded the itinerary at Cay Kho sluice gate (Nha Be District).

At these project items, the project owner—Trung Nam Construction Investment Joint Stock Company—presented progress, remaining obstacles, and operational procedures for the project upon completion to the HCMC Vice Chairman.

At Muong Chuoi sluice gate (Nha Be District), after listening to the project owner's presentation, Mr. Cuong stated: "The pandemic has passed, the BT contract addendum has been signed, so now let's execute the work."

This project commenced in 2016 and was scheduled for completion and commissioning in 2021, but failed to meet deadline due to the pandemic and various other issues.

Due to being unable to operate on schedule, several issues arose when the contract addendum expired, causing construction to halt due to lack of refinancing access.

In January 2021, the Prime Minister issued Resolution 40 on continuing project implementation. Subsequently, HCMC People's Committee held multiple meetings and adjusted the project completion timeline from 2016–2021 to 2016–2023.

Through working sessions with the State Bank of Vietnam, to refinance the project, HCMC had to approve project adjustments while signing a contract addendum with the investor—Trung Nam Construction Investment Joint Stock Company.

Following these requirements, HCMC established a negotiation team led by the Department of Planning and Investment in coordination with other departments to negotiate and sign the contract addendum with the investor (adjusting refinancing disbursement timeline, extending to September 2023, adjusting initial payment schedule until project completion in November 2023...).

Ben Nghe tidal sluice gate under 10,000-billion-VND flood control project developed by Trungnam Group

Ben Nghe tidal sluice gate under the 10,000-billion-VND flood control project

In 2022, the BT contract addendum negotiation team for the 10,000-billion-VND flood control project (comprising the Department of Finance, Department of Transportation, Urban Infrastructure Management Board, Department of Agriculture and Rural Development, Department of Construction, Department of Justice, Land Fund Development Center, and project owner Trung Nam Company) proposed two options:

1. Adjust payment timeline first, adjust land fund later.

2. Simultaneously adjust payment timeline and land fund.

Through negotiations, the project owner maintained that defining this payment land fund serves as the basis for the unit and BIDV Bank to agree on capital disbursement.

If the BT contract addendum was adjusted (negotiating payment land fund later), BIDV would not agree, causing the project to halt for a 4th time without a known completion date.

Following multiple meetings, the project's BT contract addendum was signed earlier this year. Currently, the project awaits procedures and disbursement from the State Bank of Vietnam and BIDV to resume implementation. Overall project progress currently reaches 93%.

Scale of the 10,000-Billion-VND Flood Control Project

The project to address tidal flooding in HCMC considering climate change factors - Phase 1 consists of seven components with six tidal sluice gates and 7.8 km of dykes along the Saigon River.

This work is deployed to control tidal surges and respond to climate change impacts for an area covering 570 sq km with approximately 6.5 million residents along the right bank of the Saigon River and central HCMC.

By Le Phan - Tuoi Tre Newspaper