HCMC handed over 3 land plots to member companies of Trungnam Group to pay for the BT contract of the nearly VND 10,000 billion flood control project recently restarted early this year.
According to the decision of the HCMC People's Committee on March 11, three land plots were handed over to member companies of Trung Nam Construction Investment Joint Stock Company located in Phuoc Long, Binh Quoi, and Tan My wards. These land plots are used for BT payment of the HCMC Tidal Flood Control Project (Phase 1).
The first plot, over 17,573 m² located at 232 Do Xuan Hop, Phuoc Long Ward (formerly Thu Duc City), was assigned to Trung Nam Vuong Long Co., Ltd. According to the 1/500 detailed master plan approved in late 2025, this plot will be used to construct an apartment complex.
The second plot has an area of about 3,474 m² at 762 Binh Quoi, Binh Quoi Ward (formerly Binh Thanh District), assigned to Trung Nam Dat Long Co., Ltd. Around 3,100 m² is planned for apartment construction with a 50-year land use term. The remaining area lies within the planning scope for traffic infrastructure and the Sai Gon River protection corridor. The investor is responsible for fully constructing infrastructure and handing it back to State management.
 |
Ben Nghe tidal control sluice under trial operation on the morning of Feb 2. Photo: Ha Giang
|
The third plot is Lot C8A in Area A, Tan My Ward (formerly District 7), covering 5,500 m², assigned to Trung Nam Long Thinh Co., Ltd. Under the 1/500 planning, around 5,450 m² will be used to construct apartment buildings with a 50-year term, while the remaining traffic land will be handed over to management authorities after infrastructure completion.
According to the decision of the HCMC People's Committee, the apartment construction land is allocated with land use fees, while traffic land is allocated without land use fees.
HCMC People's Committee assigned the Department of Agriculture and Environment to determine land prices as the basis for calculating land use fees and settling the BT contract with land funds. This agency will also demarcate land boundaries, hand over land on-site, and issue land use rights certificates to enterprises after financial obligations are completed.
The Department of Finance was assigned to settle the BT contract in accordance with regulations governing public-private partnership (PPP) investment projects.
The 3 newly allocated land plots belong to a total of 7 land funds HCMC plans to use for investor payment under the BT (Build-Transfer) contract signed during 2016-2020 for the nearly VND 10,000 billion flood control project. Based on the land price frame, the total estimated value of these 3 plots is around VND 2,500 billion.
Earlier, regarding land use plans, a Trung Nam representative stated that during 2026-2030, the group will focus on developing real estate projects on the allocated land funds. The enterprise expects to invest independently or partner with developers to implement projects ranging from small scale (2 years) to large urban areas (5-7 years).
The HCMC tidal flood control project broke ground in 2016 and has reached approximately 94% completion. Construction was temporarily halted from 2020 due to legal hurdles concerning BT contract mechanisms. Following directives from the Government and HCMC People's Committee, the project restarted in early February this year and is scheduled for complete completion and synchronized operation in 2026. The investor is finalizing remaining items, inspecting and calibrating systems, conducting trial runs, and completing acceptance procedures.
ACCORDING TO VNEXPRESS