4-YEAR DELAY ON HCMC 10,000-BILLION-VND FLOOD PROJECT: WHEN WILL IT FINISH?

The 10,000-billion-VND tidal flood control project has missed its completion deadline for four consecutive years, leaving residents weary of persistent flooding whenever the rainy season arrives.

Weary Wait for Local Residents

As Ho Chi Minh City enters the rainy season, Mr. Dinh The Quynh, residing in Tan Phong Ward, District 7, alongside many households along flood hotspots like Tran Xuan Soan and Le Van Luong streets, has repeatedly petitioned local authorities, asking when the 10,000-billion-VND flood control project will finally be completed.

This project aims to control flooding across a 750 km² area with approximately 6.5 million residents along the right bank of the Saigon River and central HCMC, with Trung Nam BT 1547 Company as the project owner.

Every day this project is delayed, residents across affected tidal flooding areas spanning Districts 1, 4, 7, 8, Nha Be, and Binh Chanh districts must continue enduring severe inundation.

Mr. Quynh shared: "As residents in tidal flooding zones, we earnestly hope the project will soon be completed and operationalized as originally committed by the city."

Construction site of HCMC 10,000-billion-VND tidal flood control project Phase 1 delayed for 4 years Heavy tidal flooding along Tran Xuan Soan street in District 7 HCMC awaiting flood control sluice gates

The project to manage tidal flooding in HCMC, considering climate change factors - Phase 1, with a total capital of nearly VND 10,000 billion, has missed deadlines across 2 municipal terms.

Mr. Ho Minh Khue, residing in Tan Phu Ward, District 7, expressed: "My home is near the Tan Thuan sluice gate construction site, but there were periods of quiet with no construction activity for months. Seeing a thousand-billion project—one of two key national projects directed by the National Assembly for accelerated completion—delayed four years in a row is difficult to accept. Especially as the rainy season nears, residents continue to suffer flooding."

At voter meeting sessions ahead of the 12th meeting of the 9th HCMC People's Council in late 2018, HCMC voters expressed deep concerns regarding Phase 1 of the nearly VND 10,000 billion tidal flood control project.

At that time, voter Nguyen Thi Dao (District 4) noted that the policy to implement tidal flood control was strongly supported by the public.

If completed, streets would no longer suffer tidal inundation. However, residents continuously questioned when project execution would resume.

High Determination But Pending Results

Recently, at a voter meeting prior to the 3rd session of the 15th National Assembly on May 14, 2022, opinions from Nha Be District voters were recorded. Mr. Dang Phu Thanh, Deputy Director of HCMC Department of Construction, stated: "The project has reached 90% volume and is expected to be completed and commissioned in 2023."

However, the project owner noted they are still awaiting the HCMC People's Committee to complete procedures and sign the contract addendum to continue execution. Meanwhile, the project owner incurs nearly VND 200 million daily for security, site protection, and maintaining project personnel.

The 10,000-billion-VND flood control project is a hydraulic infrastructure work under Planning 1547, approved for implementation by the 10th HCMC Party Congress (2015–2020 term) on October 18, 2015. After multiple missed deadlines, the project was expected to finish by late 2020 but failed to keep to schedule.

HCMC People Committee Chairman Phan Van Mai addressing voters regarding 10,000-billion-VND project progress

HCMC People's Committee Chairman Phan Van Mai at a voter meeting with District 7 and Nha Be District in mid-May 2022, receiving questions regarding the progress of the mega 10,000-billion-VND project.

The project owner stated the biggest current bottleneck is that the BT contract extension addendum (expired June 26, 2020) remains unsigned. Without the addendum, banks cannot disburse funds, bringing construction to a halt across multiple components.

The multi-billion project's ongoing delay has drawn direct concern from Prime Minister Pham Minh Chinh to accelerate progress.

Regarding the causes of the delay, Mr. Nguyen Huy Binh, Head of Investment Planning at HCMC Urban Infrastructure Construction Project Management Board, informed that the city is highly determined and is instructing departments to resolve issues so the project can be completed this year.

Currently, the project has completed approximately 90% volume but faces unresolved procedures concerning refinancing. With efforts from departments advising the HCMC People's Committee, administrative hurdles have largely been settled.

HCMC Department of Construction representatives anticipate construction will be accelerated to complete basic works within the year, finalizing financial settlements by 2023. However, residents in flooded areas have heard similar promises for years.

Nguyen Thanh Nhan / Nguoi Dua Tin.