ACCELERATING CONSTRUCTION PROGRESS OF CHAU DOC - CAN THO - SOC TRANG EXPRESSWAY PROJECT

On December 8, Trung Nam Construction and Machinery Erection Joint Stock Company (Trungnam EC) deployed the installation of the first girder for the package under Component Project 3, the section passing through Hau Giang Province, belonging to the Chau Doc – Can Tho – Soc Trang Expressway Project.

Following the completion of bridge spans, on December 8, Trungnam EC deployed barge transport of bridge girders to the site to facilitate installation.

Component Project 3 commenced construction on November 29, 2023, under Phase 1 of the Chau Doc – Can Tho – Soc Trang Expressway Construction Project, with Hau Giang Provincial People's Committee as the investor. The project is scaled as a 4-lane expressway with a design speed of 100 km/h and a total route length of nearly 37 km.

Trungnam EC installing the first bridge girder for Component Project 3 in Hau Giang Province
 Trung Nam Construction and Machinery Erection Joint Stock Company installing the first girder for Component Project 3, section passing through Hau Giang Province

 

According to a Trungnam EC representative, to compete in achieving milestones to bring the project to the finish line on schedule, the company organized 3 shifts and 4 teams working even on holidays. Installing the first bridge girder for packages under Component Project 3 in Hau Giang Province right on schedule plays an important role in bringing the work to completion within the prescribed timeline.

The Chau Doc - Can Tho - Soc Trang Expressway Construction Investment Project section through Hau Giang Province (Component Project 3) is invested by Hau Giang Province. To date, the locality has approved compensation and resettlement support plans for all 1,150 affected households, handing over 100% of the clean land area, equivalent to over 260 hectares. Currently, contractors are simultaneously constructing 22 of 24 bridges along the entire route, with girders installed and bridge decks poured on 5 bridges.

Construction volume executed at Component Project 3 of Chau Doc Can Tho Soc Trang expressway
 Executed volume at Component Project 3 reached nearly 30% by the end of November 2024

 

 

The executed volume at Component Project 3 reached 26% by the end of November 2024, expected to reach 36% of the contract value by the end of 2024. The local determination is to complete this project by the end of 2025 to celebrate the 14th National Congress of the Party.
In parallel, Hau Giang Province deployed investment procedures for 6 resettlement areas covering over 23 hectares serving 2 projects. To date, resettlement projects have reached completion and been handed over to District People's Committees to arrange resettlement for affected citizens.

Phase 1 of the Chau Doc - Can Tho - Soc Trang Expressway Project has a total length of 188.2 km passing through 4 provinces and cities: An Giang, Can Tho, Hau Giang, and Soc Trang.

The starting point connects to National Highway 91 in Chau Doc City (An Giang) and the endpoint intersects with Nam Song Hau National Highway, connecting to the access road of Tran De Port (Soc Trang), carrying a total investment capital of VND 44,691 billion. The entire route is expected to reach full completion and commercial operation in 2027.

Route map of Chau Doc Can Tho Soc Trang expressway phase 1
 Phase 1 of the Chau Doc - Can Tho - Soc Trang Expressway Project has a total length of 188.2 km passing through 4 provinces and cities: An Giang, Can Tho, Hau Giang, and Soc Trang

 

< p> Component Project 1 in An Giang Province spans 57.2 km, Component Project 2 in Can Tho City spans 37.2 km, Component Project 3 in Hau Giang Province spans nearly 37 km, and Component Project 4 in Soc Trang Province spans 56.9 km.

 

In Phase 1, the project is designed with a phased scale of 4 lanes and a design speed of 100 km/h. In the complete phase, the project will be scaled to 6 lanes.
The horizontal arterial expressway project Chau Doc – Can Tho – Soc Trang helps complete the transport network, leveraging efficiency for already invested and ongoing expressway projects. This project also aims to connect economic centers, international border gates, and seaports, meeting transportation demand along the Northwest – Southeast economic corridor, creating synchronized transport infrastructure and a prerequisite for socio-economic-cultural development while ensuring national defense and security in the Mekong Delta region.

Minh Triet
(ACCORDING TO CONG LY NEWSPAPER)

 