ACCELERATING FINAL ITEMS OF HCMC'S VND 10,000 BILLION FLOOD CONTROL PROJECT

The VND 10,000 billion flood control project in HCMC has entered its sprint phase, with many tidal control sluices reaching over 90% progress, scheduled for trial operation from September to November.

Accelerating final items of HCMC VND 10000 billion flood control project

The Project "Solving tidal flooding in HCMC area, taking into consideration climate change factors", also known as the VND 10,000 billion flood control project, is pushing forward construction execution to be brought into operation.

Tidal flood control project in HCMC entering sprint phase

Restarted in early February 2026, the project consists of 6 major tidal control sluices, 2 small sluices, approximately 6 km of dykes/embankments, and 43 small-scale tidal control sluices.

Construction progress on HCMC tidal flood control sluices

As recorded by VTC News reporters on September 18 at Tan Thuan tidal control sluice, the construction unit is concentrating on completing final items, preparing for trial operation expected in October 2026.

Tan Thuan tidal control sluice preparing for trial operation in October 2026

On site, substantial machinery and workers have been mobilized to finish the management building cluster, pumping station, generator house, and technical infrastructure, while landscaping the project area.

Machinery and workers completing management building and pumping station

Electro-mechanical equipment, pumps, and the SCADA control system are also being installed and integrated.

Laying electro-mechanical equipment and SCADA control system integration

The construction unit has simultaneously completed lock gate installation, dredging, and suction erosion treatment in upstream areas, alongside finishing embankments and gabion mattresses for canal bed reinforcement.

Installing lock chamber gates and canal bed reinforcement

Mr. Nguyen Van Tinh (residing in Tan Thuan Ward) expressed delight as the project nears completion. "We have awaited project completion for many years because along this route, every high tide season brings flooding. At times, heavy rain combining with peak tides turns roads into rivers," Mr. Tinh said.

Local residents expressing joy as HCMC flood control project nears completion

According to residents, over past years, this area frequently suffered from flooding due to heavy rain and high tides. Therefore, accelerated project progress toward trial operation brings high anticipation.

Area previously affected by heavy rain and high tides in HCMC

At Phu Dinh tidal control sluice, scheduled for trial operation in November 2026, progress currently stands at approximately 93%.

Phu Dinh tidal control sluice reaching 93 percent construction progress

On-site observations show that both sides of the access road leading to the sluice gate have been renovated and cleared. The access road is paved wide with asphalt, and technical infrastructure items continue to reach completion.

Asphalt paved access road leading to Phu Dinh sluice gate

The construction unit is finalizing the management building, pump station house, and generator area; installing handrails, planting trees, and laying gabion mattresses. Four embankment segments are also being accelerated. Concurrently, electro-mechanical equipment and the SCADA system are being installed, while lock gates are assembled in preparation for installation steps and trial runs.

Electro-mechanical and SCADA control equipment installation at Phu Dinh

Ms. Lam Thi Soc (residing in Phu Dinh Ward) shared that residents have waited years for project completion. "For nearly a month now, as the project nears the finish line, everyone is thrilled," Ms. Soc stated.

Local residents in Phu Dinh ward looking forward to project trial runs

According to Trung Nam Construction Investment Joint Stock Company, the project investor, many major items currently stand at 92-99% completion. Execution units are focusing on finishing remaining works, striving for trial runs of individual sluice gates between September and November 2026.

Ben Nghe Tan Thuan and Phu Xuan sluices achieving over 95 percent progress

Specifically, Ben Nghe sluice reached 99% progress, having completed inspection and project handover. Tan Thuan sluice reached 95%, expecting trial operation in October 2026. Phu Xuan sluice reached 95%, expecting trial operation in October 2026.

Muong Chuoi and Cay Kho sluice gates targeting November trial runs

Muong Chuoi sluice reached 94%, expecting trial operation in November 2026. Cay Kho sluice reached 94%, expecting trial operation in October 2026. Phu Dinh sluice reached 93%, expecting trial operation in November 2026.

Cau Kinh and Ba Buom tidal control sluices reaching 96 percent completion

Cau Kinh and Ba Buom sluices reached 96% progress, completing post-embankment tiling, operation roads, management buildings, landscaping, and tree planting. Electro-mechanical equipment and SCADA systems continue installation to finalize technical conditions for trial runs. These two sluices are expected to begin trial operation in September 2026.

Embankment and dyke sections reaching 92 percent overall progress

For dyke and embankment sections, progress stands at approximately 92%. Currently, units are completing back-embankment works, riprap in front of embankments, 2M sluice houses, and along-route landscaping. Simultaneously, handrails and electro-mechanical devices are being installed; SCADA systems are synchronized, and sluice gates for 2M sluice and small dyke sluices continue deployment as scheduled.

Central management building under final architectural completion

At the central management building, main block structures, warehouses, workshops, interior finishes, and remaining architecture are being finalized. Construction units are also completing internal roads, tree landscaping, and integrating electro-mechanical equipment with the automated SCADA control system.

Central SCADA control system scheduled for full synchronization in November 2026

The central control system is scheduled for full synchronization in November 2026, serving signal reception, monitoring, and operation of the entire project.

According to Luong Y - VTCNews