The VND 10,000 billion flood control project in HCMC has entered its sprint phase, with many tidal control sluices reaching over 90% progress, scheduled for trial operation from September to November.
The Project "Solving tidal flooding in HCMC area, taking into consideration climate change factors", also known as the VND 10,000 billion flood control project, is pushing forward construction execution to be brought into operation.
Restarted in early February 2026, the project consists of 6 major tidal control sluices, 2 small sluices, approximately 6 km of dykes/embankments, and 43 small-scale tidal control sluices.
As recorded by VTC News reporters on September 18 at Tan Thuan tidal control sluice, the construction unit is concentrating on completing final items, preparing for trial operation expected in October 2026.
On site, substantial machinery and workers have been mobilized to finish the management building cluster, pumping station, generator house, and technical infrastructure, while landscaping the project area.
Electro-mechanical equipment, pumps, and the SCADA control system are also being installed and integrated.
The construction unit has simultaneously completed lock gate installation, dredging, and suction erosion treatment in upstream areas, alongside finishing embankments and gabion mattresses for canal bed reinforcement.
Mr. Nguyen Van Tinh (residing in Tan Thuan Ward) expressed delight as the project nears completion. "We have awaited project completion for many years because along this route, every high tide season brings flooding. At times, heavy rain combining with peak tides turns roads into rivers," Mr. Tinh said.
According to residents, over past years, this area frequently suffered from flooding due to heavy rain and high tides. Therefore, accelerated project progress toward trial operation brings high anticipation.
At Phu Dinh tidal control sluice, scheduled for trial operation in November 2026, progress currently stands at approximately 93%.
On-site observations show that both sides of the access road leading to the sluice gate have been renovated and cleared. The access road is paved wide with asphalt, and technical infrastructure items continue to reach completion.
The construction unit is finalizing the management building, pump station house, and generator area; installing handrails, planting trees, and laying gabion mattresses. Four embankment segments are also being accelerated. Concurrently, electro-mechanical equipment and the SCADA system are being installed, while lock gates are assembled in preparation for installation steps and trial runs.
Ms. Lam Thi Soc (residing in Phu Dinh Ward) shared that residents have waited years for project completion. "For nearly a month now, as the project nears the finish line, everyone is thrilled," Ms. Soc stated.
According to Trung Nam Construction Investment Joint Stock Company, the project investor, many major items currently stand at 92-99% completion. Execution units are focusing on finishing remaining works, striving for trial runs of individual sluice gates between September and November 2026.
Specifically, Ben Nghe sluice reached 99% progress, having completed inspection and project handover. Tan Thuan sluice reached 95%, expecting trial operation in October 2026. Phu Xuan sluice reached 95%, expecting trial operation in October 2026.
Muong Chuoi sluice reached 94%, expecting trial operation in November 2026. Cay Kho sluice reached 94%, expecting trial operation in October 2026. Phu Dinh sluice reached 93%, expecting trial operation in November 2026.
Cau Kinh and Ba Buom sluices reached 96% progress, completing post-embankment tiling, operation roads, management buildings, landscaping, and tree planting. Electro-mechanical equipment and SCADA systems continue installation to finalize technical conditions for trial runs. These two sluices are expected to begin trial operation in September 2026.
For dyke and embankment sections, progress stands at approximately 92%. Currently, units are completing back-embankment works, riprap in front of embankments, 2M sluice houses, and along-route landscaping. Simultaneously, handrails and electro-mechanical devices are being installed; SCADA systems are synchronized, and sluice gates for 2M sluice and small dyke sluices continue deployment as scheduled.
At the central management building, main block structures, warehouses, workshops, interior finishes, and remaining architecture are being finalized. Construction units are also completing internal roads, tree landscaping, and integrating electro-mechanical equipment with the automated SCADA control system.
The central control system is scheduled for full synchronization in November 2026, serving signal reception, monitoring, and operation of the entire project.
According to Luong Y - VTCNews