HCMC Department of Planning and Investment has been urgently tasked with leading and coordinating with departments and related units to review and address proposals from the investor of the 10,000-billion-VND flood control project.

Vice Chairman of HCMC People's Committee Bui Xuan Cuong (second from right) during an on-site inspection of the 10,000-billion-VND flood control project
HCMC People's Committee Office has issued a document to HCMC Department of Planning and Investment conveying instructions from Vice Chairman Bui Xuan Cuong regarding resolving obstacles related to Phase I of the project to manage tidal flooding in HCMC considering climate change factors (10,000-billion-VND flood control project).
Accordingly, Mr. Cuong instructed the Department of Planning and Investment to urgently lead and coordinate with relevant departments and agencies to review and handle proposals submitted by Trung Nam Construction Investment Joint Stock Company in its document sent to Deputy Prime Minister Tran Luu Quang on February 26, 2024.
Simultaneously, the department must strictly execute instructions from Deputy Prime Minister Tran Luu Quang in the Government Office's dispatch dated March 7, 2024.
The Department of Planning and Investment must submit advisory proposals and draft documents to the HCMC People's Committee to report to the Government task force before March 13.
Earlier, on March 7, the Government Office issued a dispatch conveying the direction of Deputy Prime Minister Tran Luu Quang, Head of the Government Task Force on unlocking HCMC's 10,000-billion-VND flood control project.
The Deputy Prime Minister directed the Chairman of HCMC People's Committee, Deputy Head of the Task Force, to urgently execute assigned tasks on resolving project obstacles and report to the task force before March 15.
Along with this, the HCMC Chairman was tasked with proactively directing relevant city agencies to review and process petitions from Trung Nam Construction Investment Joint Stock Company.
In its February 26 document to Deputy Prime Minister Tran Luu Quang, Trung Nam Construction Investment Joint Stock Company noted that on November 5, 2023, the Government Office released conclusion notices from Deputy Prime Minister Tran Luu Quang directing the review and removal of hurdles for HCMC's flood control project.
Despite over 3 months passing since the Government task force meeting and conclusion notice, the project has yet to restart, even though the investor submitted numerous petition dispatches to the City Party Committee and People's Committee requesting prompt direction on tasks within municipal authority.
Therefore, the company petitioned the Deputy Prime Minister for support and guidance to enable early resumption of construction, completion, and commissioning to maximize investment efficiency and avoid massive daily loan interest losses.
Conflicting Opinions on Capital Unlocking Options for the 10,000-Billion-VND Flood Control Project
- In December 2023, HCMC Vice Chairman Bui Xuan Cuong instructed relevant units to advise the city on capital sources to resolve bottlenecks for the 10,000-billion-VND project.
- According to reports on implementing Government Resolution 40 regarding the project, HCMC proposed three options:
- Option 1: City makes payments for completed work volume to the investor simultaneously in land and cash, matching agreed payment schedules.
- Option 2: HCMC Financial Investment State Company (HFIC) provides loans from its operational capital. This option allows HFIC to proactively lend so the investor can complete construction.
- Option 3: HFIC receives budget entrustment from HCMC budget per Government Decree 147 issued in 2020. Specifically, HCMC entrusts budget (~VND 1,800 billion) to HFIC for HFIC to lend to the investor to finish construction.
After project acceptance, HCMC will settle payments with the investor under signed BT contracts and addenda. The investor will then repay HFIC, and HFIC will return entrusted capital to HCMC budget.
Following analysis, HCMC deemed Option 3 most feasible with regulatory grounds. The People's Committee requested departments to clarify execution details.
By January 2024, Vice Chairman Bui Xuan Cuong chaired a meeting on financial plans, payment land funds, and State Audit recommendations.
However, the Department of Finance noted the entrustment option may not align with Ministry of Finance regulations, thus lacking grounds to advise on entrustment, while requesting HFIC to clarify which unit advises HCMC to issue entrustment decisions.
By Tien Long / Tuoi Tre Newspaper