The previous electricity planning failed to accurately forecast the development of renewable energy, leading to passivity and a lack of synchronization between policy and market, as well as generation and grid planning, causing current shortcomings. Recently, a coalition of 10 alliances and organizations representing more than 200 Vietnamese scientists in clean energy, environmental protection, public health, and climate change response submitted comments on several contents of the Draft Power Development Plan VIII (PDP8) released by the Ministry of Industry and Trade in early September 2021. Notably, this coalition emphasized removing unconstructed coal power projects from the Plan while introducing solutions to develop renewable energy (RE).

Exhibiting "Steps Backward"


The coalition stated that the new Draft Power Development Plan VIII still outlines an energy development roadmap that runs counter to global trends. Continuing to heavily develop new coal power over the next 10 years places Vietnam among a small minority of nations opposing global efforts to reduce fossil fuels. Meanwhile, Vietnam is one of the countries most severely impacted by climate change. Concerns over limiting renewable energy development in draft Power Development Plan VIII PDP8
Meanwhile, developing green and sustainable energy is a major policy of the Party and State, as well as the shared aspiration of the entire population. This needs to be reflected in the National Power Development Plan for 2021–2030, Vision to 2045 (PDP8), currently being revised by the Ministry of Industry and Trade before submission to the Government for approval.

“The new draft Power Development Plan VIII dated September 5, 2021” represents a lag behind global green and clean energy trends, as it continues to shape Vietnam's energy future with heavy reliance on fossil fuels while curbing RE development. In fact, this draft exhibits 'steps backward' compared to the March 2021 draft by adding approximately 3,000 MW of coal power and cutting about 8,000 MW of renewable energy by 2030. Thus, over the next 10 years, new coal power capacity will increase by nearly 20,000 MW, whereas solar power will only increase by about 2,000 MW with no offshore wind power development,” the coalition highlighted.

Furthermore, the coalition affirmed that restricting RE development over the next 10 years will cause Vietnam to fall far behind global energy science and technology advancements. While many countries are capitalizing on opportunities and accelerating technological solutions to maximize RE advantages—such as energy storage, smart grids, distributed renewable energy combined with agriculture, transport, hydrogen production...—PDP8 chooses to restrain RE and lacks a roadmap to promote these technological advances.

“Currently, energy technology is advancing very rapidly, requiring strategic vision, forecasting capability, and breakthrough policy steps to seize new opportunities. However, the current draft fails to demonstrate this and is repeating the failed lessons of previous power master plans, which 5 years ago failed to accurately forecast RE growth, leading to passivity and a mismatch between policy and market, generation and grid planning, causing current inadequacies,” the feedback emphasized.

Losing Opportunities to Attract Investment Capital


Addressing the power source development roadmap in PDP8, the coalition pointed out that continuing coal power projects is an expensive choice, causing repercussions for the overall economy and proving unfeasible to implement. Most new coal power projects will rely on imported coal, while coal prices are skyrocketing.

In fact, coal prices in the first 6 months of 2020 were at USD 98.8/ton, surging to USD 159.7/ton this year—a 150% increase. Meanwhile, the coal price forecasted in the draft for 2030 is only USD 75/ton. Thus, coal power generation costs presented in the draft are lower than reality. Including external costs (environmental and health costs), coal power generation costs could increase by another 5 US cents/kWh, reaching 15-16 US cents/kWh, making it more expensive than all forms of renewable energy.

Notably, with a high proportion of fossil fuel power, Vietnam's export goods will face carbon tariffs from developed countries and lose competitive advantages. Concurrently, Vietnam will miss out on attracting foreign direct investment (FDI) from multinational corporations seeking clean power to fulfill their committed carbon neutrality targets.
Global divestment movement from fossil fuels and coal thermal power generation
In reality, lessons from Revised PDP VII showed a series of delayed coal power projects due to financing access difficulties. This challenge will escalate as numerous countries commit to phasing out coal power, the divestment movement from fossil fuels intensifies, and the last remaining countries supporting coal development announce stops on funding or shift investments toward clean energy.

“The Ministry of Industry and Trade needs to remove unconstructed coal projects from the master plan, while prioritizing policy solutions to resolve immediate difficulties and boost sustainable RE development in the future. We commit to mobilizing expertise and professional knowledge, contributing voluntarily alongside the Ministry of Industry and Trade and relevant agencies to revise and refine Draft PDP8 to meet requirements before submitting to the Prime Minister for approval,” the coalition recommended./.