Few could imagine a mega offshore wind project, with construction conditions vastly more challenging than onshore, being built during unfavorable weather and pandemic conditions; yet Trung Nam reached the finish line right on schedule, commercially operating 25 wind turbines ahead of the "G-hour".
REACHING OUT TO THE OPEN SEA
Beneath the waters, super-heavy crane barges hoisted the national flag alongside a flag bearing the
Trungnam Group logo, fluttering proudly in the afternoon breeze. Amidst a forest of wind turbines—resembling giant windmills operating in the sea—attendees at the ceremony felt deeply moved and proud as a 100 MW wind farm was finally completed despite facing countless hardships.
Having been closely attached day and night to the project's construction process, Mr. Nguyen Tam Tien – General Director of Trungnam Group – did not wear the reflective vest and safety helmet of a construction engineer today as usual, but instead put on a formal suit to witness a special flag-raising ceremony filled with emotion.
Watching the national flag fly high, Mr. Tien shared that this offshore wind project serves as testament to the capability, standing, and potential of Vietnamese enterprises to construct large-scale offshore wind projects at "lightning speed". This is also the first offshore wind project built by Trungnam Group, remaining one of the few large-scale offshore wind power projects in Vietnamese waters to date.
According to Mr. Tien, the pride of this project lies in Vietnamese private enterprises "reaching out to the open sea"—investing in domestic clean energy while proving the growing strength of Vietnamese private firms in constructing national works, creating jobs for local workers, and contributing resources to national economic growth. For offshore wind projects, each turbine pillar stands as a benchmark of sovereignty and marine economy built by Vietnamese hands.
OVERCOMING HARDSHIPS TO ERECT WIND TURBINES AT SEA
For wind power developers in Vietnam, the past year has been an unprecedentedly vibrant period for the renewable energy industry, yet also immensely difficult as projects faced severe obstacles from COVID-19, global supply chain disruptions, and prolonged lockdowns affecting equipment logistics.
For Trungnam Group, despite executing multiple onshore and offshore projects simultaneously, the unwavering efforts of the entire team ensured all projects reached completion on schedule. Specifically for Dong Hai 1 Wind Power Project, construction crews faced unprecedented challenges.
Kicking off in late Q4 last year, after over 10 months of implementation, Trung Nam Tra Vinh 1 Wind Power JSC transported nearly 70,000 tons of equipment and raw materials across over 12,000 km to the project site.
Throughout construction, 1,100 engineers and workers directly executed works across a 14km access bridge at sea, utilizing over 18,000 tons of steel and driving 115,000 meters of steel piles directly into the seabed to build turbine foundations.
Mr. Do Van Kien – Director of Trung Nam Tra Vinh 1 JSC – shared that turbine installation required crane machinery with heights of 130m and lifting capacity exceeding 1,200 tons to assemble 75 wind blades onto turbine towers at a hub height of 105m.
According to Mr. Kien, alongside challenges of working with massive equipment, harsh climate and hydrological obstacles in the area directly impacted progress, particularly as the sea frequently experienced strong monsoons and high swells. |
 |
CONTINUING TO REACH OUT TO THE OPEN SEA
Standing on this offshore wind farm, Mr. Nguyen Quynh Thien – Vice Chairman of Tra Vinh Provincial People's Committee – noted that during project implementation, pandemic challenges and natural marine conditions did not deter Trungnam Group from fulfilling the Government's "dual goal" and commitments to the province.
According to Mr. Thien, within just 10 months of execution, 25 European-technology wind turbines rising over 105m high above the East Sea now generate clean electricity daily, delivering economic benefits to the province and setting high expectations for Tra Vinh's offshore wind future.
Vice Chairman of Tra Vinh Provincial People's Committee affirmed that Tra Vinh's wind potential remains untapped to its full capacity, expressing the province's desire to partner with enterprises to unlock this new economic spearhead. According to Trungnam Group, despite facing numerous hardships, the engineering team overcame obstacles, adapted, and innovated to accelerate construction.
Beyond optimizing execution timelines, construction steps were meticulously planned with detailed technical contingency options to minimize risks at sea, ensuring labor safety while complying with wave and wind conditions.
Mr. Nguyen Tam Tien shared that although this was the company's first offshore wind project, completing the installation of 25 wind turbines represents Trungnam Group's success in meeting the challenge of reaching out to the open sea, fulfilling its "dual goal" commitment to prevent pandemic spread while driving economic development.
Dong Hai 1 Wind Power Project serves as concrete proof of Trungnam Group's sustainable orientation toward renewable energy and clear evidence of its engineering team's capacity to execute large-scale offshore wind projects in the future.