GROUNDBREAKING CEREMONY FOR CA NA GENERAL SEAPORT (PHASE 1)

On the afternoon of August 25, 2020, in the Ca Na coastal area, Phuoc Diem commune, Thuan Nam district, Trungnam Group organized the Groundbreaking Ceremony for Phase 1 of the Ca Na General Seaport Project. 
Phase 1 of the Ca Na General Seaport Project was granted Investment Decision No. 656/QD-UBND on April 26, 2018, and Adjustment Decision No. 246/QD-UBND on August 24, 2020, by the Ninh Thuan Provincial People's Committee, securing full legal foundations and operational directives.

 Groundbreaking ceremony for Phase 1 of Ca Na General Seaport project - Trungnam Group


Phase 1 of the project has approved 1/500 detailed planning covering a total area of over 108 hectares, with main functional zones including two 70,000 – 100,000 DWT (Deadweight Tonnage) berths and one 20,000 DWT berth alongside warehouse and service infrastructure areas. The designed throughput capacity reaches approximately 3.3 million tons of cargo per year.

 Perspective view of Ca Na General Seaport Phase 1 - Trungnam Group


The project encompasses all planned components: berths, jetties, yards, warehouses, auxiliary works, services, technical infrastructure hubs, transportation, and green spaces. Once operational, the seaport will integrate smart technologies into port operations, facilitating rapid and efficient cargo handling while targeting sustainable development goals.

 Mr. Nguyen Tam Tien General Director of Trungnam Group speaking at Ca Na Seaport groundbreaking


Upon operation, the project will create favorable conditions for production and processing across industrial zones and clusters operating in Ninh Thuan province, the South Central region, and the Central Highlands. Furthermore, the project plays a pivotal role in supporting the transportation of equipment for renewable energy projects being invested in and constructed throughout the province.

 Provincial leaders and delegates performing groundbreaking ceremony for Ca Na Seaport - Trungnam Group


According to the construction roadmap, Berth No. 1 (70,000 – 100,000 DWT) is scheduled for completion and commercial operation by December 2022. Construction on Berth No. 2 (70,000–100,000 DWT) will commence in January 2023, with operational status targeted by October 2025. Subsequently, construction of the 20,000 DWT berth will begin in November 2025, with completion and commissioning targeted for August 2026.

 Trungnam Group presenting sponsorship funds for local community infrastructure


On this occasion, Trungnam Group also presented over VND 7.7 billion in sponsorship funds to support local infrastructure construction and community facility renovations, including: VND 6 billion for resettlement infrastructure and drainage systems in Lac Tan 3 hamlet, Phuoc Diem commune; VND 1.3 billion for the stadium fence in Nhi Ha commune; and VND 462 million for facility repairs and equipment at Hieu Thien School, Phuoc Ninh commune, Thuan Nam district.

 