The trial re-operation of Ben Nghe sluice gate and the relaunch of the entire project mark an important step toward bringing the project into synchronized operation, optimizing tidal control efficiency.
On February 2, Trung Nam Construction Investment Joint Stock Company coordinated with the HCMC People's Committee and relevant departments to organize the trial re-operation of the Ben Nghe tidal control sluice and relaunch the project "Solving tidal flooding in HCMC area, taking climate change factors into consideration (Phase 1)".
The project relaunch demonstrates the determination to overcome obstacles, accelerate progress on key infrastructure, and strictly implement directives from the Politburo, the Government, and the Central Steering Committee on anti-wastefulness.
RESTARTED AFTER 5 YEARS OF SUSPENSION
According to Dan Tri reporters, at 9:00 AM on the same day, when the signal horn sounded, the hydraulic cylinder system began operating, raising the steel gate panel from the bed of Ben Nghe Canal by about 3 meters. The steel gate splits the water flow, preventing water from the Sai Gon River from entering inner-city canals during high tides.
After the steel gate panel was lifted, high-capacity pump systems were also activated, pumping water from inner-city canals into the Sai Gon River. The operation process took place under the observation of HCMC People's Committee Vice Chairman Bui Xuan Cuong, department leaders, and investor representatives.
The HCMC tidal flood control project had been interrupted for an extended period. To date, all items have undergone an overall review and status assessment as a basis for further execution. Overall progress has reached about 94%, with main items basically complete, entering final finishing, testing, calibration, system connection, and trial runs according to procedure.
 |
|
Steel gate panel dividing the canal to regulate water at Ben Nghe Sluice
(Photo: An Huy)
|
At Ben Nghe Sluice, the construction unit dredged the riverbed and completed the installation of the SCADA automated control system. Remaining sluices, including Tan Thuan, Phu Xuan, Muong Chuoi, Cay Kho, Phu Dinh, Cau Kinh, and Ba Buom, completed revetments, management houses, landscaping, installation of electromechanical equipment, automated control systems, and lock gate assembly preparation. The riverbank dike line was filled with sand, slope revetments reinforced, and auxiliary items completed.
The trial re-operation of Ben Nghe Sluice and the relaunch of the entire project serve as crucial steps toward operating the project synchronously, maximizing tidal control efficiency, supporting rainwater drainage, and enhancing urban landscape and environment.
HCMC designates 2026 as the time to complete and put the project into operation. Once operational, the work will contribute to controlling tidal flooding in inner-city and downtown areas, while elevating urban drainage efficiency under the master plan approved by the Prime Minister.
DETERMINED TO COMPLETE IN 2026
Mr. Nguyen Tam Tien, CEO of Trungnam Group, stated that the project was paused for about 5 years. Without obstacles, it would have been completed in 2018-2019. However, due to administrative reviews, the project was temporarily suspended.
The project pause affected daily life and traffic for local residents while causing losses for the investor and contractors. "I sincerely apologize to residents in the project area for the unwanted impacts. We understand the people's expectations. Under the guidance of HCMC leaders, the Party Central Committee, and the Government, the project was restarted. In fact, we prepared and resumed work a few months ago," Mr. Tien shared.
According to Mr. Tien, Ben Nghe Sluice is the largest submerged sluice gate in Vietnam. When idle, it remains submerged to ensure normal waterway navigation; when operational, it rises, pumping water from inner-city channels into the river.
The project targets 4 goals: tidal prevention; pumping support for urban flood control; water level maintenance and canal environmental protection; and salinity intrusion prevention during high sea tides.
 |
|
Mr. Nguyen Tam Tien, CEO of Trungnam Group, speaking at the ceremony
(Photo: An Huy)
|
The investor commits to completing and bringing the entire project into operation in 2026. Completed items will be operated as finished, aiming to shorten the overall timeline compared to the plan.
Mr. Tien also noted that most equipment was imported from Europe. The prolonged suspension caused the investor to lose warranty periods. Therefore, the unit proposed that HCMC allow them to operate the project for 5-10 years, committing to equipment warranties corresponding to the operational duration.
" Operating 6 major sluices, 2 medium sluices, 12 small sluices, and the dike system is not simple, especially ensuring waterway traffic safety. We have a team handling both construction and operation. From now until the end of 2026, the goal is to complete the entire project," Mr. Tien added.
HIGH EXPECTATIONS FOR EFFECTIVE FLOOD CONTROL
Mr. Bui Xuan Cuong, Vice Chairman of the HCMC People's Committee, stated that the tidal flood control project has been underway for many years and has faced numerous difficulties. To date, over 90% of construction output has been completed. Recently, the Government issued Resolution 212 to unblock bottlenecks, which, together with strong support from the HCMC People's Committee, departments, and investors, has gradually unblocked the project.
According to Mr. Cuong, the total investment capital was approved in November 2025. The State Audit Office is re-auditing the total investment, and HCMC will adjust accordingly after receiving official audit findings.
The investor and related units restarted the project in December 2025, deploying construction on items such as Ben Nghe Sluice, Muong Chuoi Sluice, and operational buildings. Re-operating Ben Nghe Sluice is the initial outcome after two months of relaunching, making it the first of 6 main sluices to be put into operation.
" On behalf of HCMC People's Committee, I commend departments and the investor for demonstrating responsibility, courage, determination, and creativity in completing core procedures. Next steps, such as land allocation to the investor, will continue to be accelerated," Mr. Cuong said.
 |
|
Mr. Bui Xuan Cuong, Vice Chairman of HCMC People's Committee, speaking at the tidal project relaunch ceremony
(Photo: Khoa Nguyen)
|
The HCMC Vice Chairman affirmed that currently, the project meets conditions to concentrate resources according to investor commitments, aiming for full completion in 2026. Items will be commissioned as completed.
Upon completion, the project will not only control tidal flooding but also regulate river and canal water levels, proactively cope with heavy rains combined with high tides, improve urban landscapes, maintain water levels, and develop waterway transport. Specifically, operating Ben Nghe Sluice will help control flooding in downtown HCMC.
" Past project delays affected daily life, transport, and corporate operations. I hope citizens and businesses continue sharing and accompanying us. In 2026, the city will coordinate to accelerate progress to commission the project, overcoming flooding in affected areas," Mr. Bui Xuan Cuong emphasized.
ACCORDING TO DAN TRI